WEST WHITELAND TOWNSHIP
Planning Commission
Agenda
Tuesday, January 6, 2026
7:00 P.M.
Etiquette for
hybrid meetings
Meeting will be held in-person and via Zoom
Register for Zoom Meeting
Call by Phone: 1-646-558-8656
Meeting ID: 873 0897 0242
Passcode: 507637
Meeting Packets can be found on the Township website.
Reminder to meeting participants: Please speak clearly into the microphone.
CALL TO ORDER
REORGANIZATION
REVIEW OF MEETING MINUTES
1. Approval of Meeting Minutes: December 2, 2025
PUBLIC COMMENT/CONCERNS/QUESTIONS
Comments or questions regarding issues NOT on the agenda should be raised at this time.
Members of the public will have an opportunity to ask questions and comment upon agenda
items during the discussion on those items.
PLANS
No plans are complete for review for this agenda.
NEW BUSINESS
OLD BUSINESS
DISCUSSON
Data center ordinance update.
ADJOURNMENT
Next Meeting: January 20, 2025
MEMORANDUM
TO:
Planning Commission
FROM: John R. Weller, AICP
Director of Planning and Zoning
SUBJECT: Discussion on zoning for data centers
DATE:
January 2, 2022
We have already had some preliminary discussion regarding zoning for data centers, largely
prompted by the data center project recently approved by East Whiteland on a property
abutting West Whiteland. Of course, data centers have also been in the news a lot, often in
regard to negative impacts on the community where they’re located.
The Supervisors have directed us to prepare draft Zoning regulations to address data centers.
The Commission will recall that, since data centers are a legal use of property, we do not have
the option of simply prohibiting them, but we can regulate them. At this time, Staff is still in
the process of researching the aspects of data centers that are best regulated by Zoning as well
as identifying best practices from other communities. In December 2025, we virtually attended
a webinar from Penn State that addressed common community concerns and also provided
some insight into what data center developers look for when selecting a site for their project.
The purpose of tonight’s discussion is to bring the Commission up to date on our
research and to identify and/or prioritize Commission concerns to be addressed as
we craft the draft regulations for inclusion in our Zoning Ordinance.
The current working definition we have for a “data center” is “A building or a portion of a
building that houses computer systems and associated components, which may
include but are not limited to servers, switches, routers, communication hardware,
and back-up energy sources such as battery storage.” As we have noted previously, a
“data center” may be as small and innocuous as the server room here in the Township Building.
The PSU webinar confirmed this, noting that the industry currently has four classifications for
data centers:
•
MICRO data centers are smaller than 5,000 sq.ft., and are typically accessory uses with little
to no impact on surrounding properties.
•
A SMALL data center has between 5,000 sq.ft. and 20,000 sq.ft. of floor area. At this size,
the data center could still be an accessory use, occupying a portion of a larger building, or
the sole occupant of a moderately sized building. For reference, consider that the Raymour
and Flanigan store across the street has a footprint of about 37,000 sq.ft. In either case,
the impact upon surrounding properties is still negligible.
•
An AVERAGE data center will be up to 100,000 sq.ft., containing up to 5,000 servers;
•
A HYPERSCALE data center is anything larger than an average data center.
We intend to focus our regulations on average and hyperscale centers, as these have the
greatest impact and are most likely to be the principal use of a property.
1
Since data centers are power-hungry, Pennsylvania has emerged as a popular location for data
centers, due to the prevalence of relatively cheap power from natural gas and nuclear-powered
generators. In addition to cheap power, data center developers also look for:
•
a robust power grid with existing redundancy;
•
existing broadband infrastructure (proximity to a minimum of two reliable fiber networks);
•
available land – a minimum of fifty acres, relatively level, with low vulnerability to natural
disasters;
•
readily available water for cooling (although other cooling options may be considered); and
•
separate from residential areas.
In contrast, community concerns include:
•
impact upon energy resources (i.e., the potential for rate increases for existing users in
response to the cost of building new generating facilities);
•
impact upon water supply;
•
environmental impact of very large buildings (stormwater runoff, micro-climate,
groundwater recharge, etc.);
•
noise, particularly related to cooling equipment and outdoor emergency generators (which
need to be tested regularly); and
•
what happens to the very large buildings should the data center become obsolete.
Our current regulations allow data centers as a conditional use in the General Industrial (I-2)
zoning district under the general “catch all” provision in §325-19.B(11)(i) of the Zoning
Ordinance. In addition, we already have stormwater management regulations and performance
standards to address at least the most critical environmental concerns. However, these are
somewhat generic and may not be best suited to addressing impacts unique to data centers –
including the question of whether the I-2 district is really the best location for them.
Our intent is to have regulations that will address these concerns (and others that we may yet
identify) without unduly restricting the development of data centers. After all, we all rely upon
these facilities in our day-to-day lives: access to data is now a critical consideration for
businesses and part of the high quality-of-life we want for our residents.
PC MMO’s – Miscellaneous\2026\260102 – data center zoning
2
The government’s own published record — read it yourself, then decide what to do about it.
The facilities, the coverage, and the local record for this community.
Not yet recorded. The record stays open — outcomes are added as minutes and vote results are published.
Provenance
Where this record came from. Every source is listed, permanently.
- Agenda Watch · Aug 16, 2026
Permanent ID DKT-2026-000830 — this record is never deleted.
Record history
Every change to this record, logged as it happened.
- Aug 16, 2026 Filed on the Docket
- Aug 16, 2026 Full document archived — public record
← The full Docket · every meeting, vote, and action on the permanent record · also in the National Record Index.